Google Project Management - Project Planning: Module2 Challenge

Project Management Quiz: Planning, Execution, and Team Management

Question 1: What are examples of documents used in project management?

Correct Answer: The project charter that defines the project and outlines project goal details, RACI charts that define roles and responsibilities for individuals on a team

Question 2: What does "slack" refer to in project management?

Correct Answer: stakeholder time

Question 3: What does "critical path" refer to in project management?

Correct Answer: critical path

Question 4: What is one way a project manager can improve team dynamics?

Correct Answer: Practice empathy

Question 5: What purpose do milestones serve in project management?

Correct Answers: They can demonstrate how their individual tasks connect to other tasks in the project, They can illustrate when they need to complete their individual tasks, They provide clear context about work project details.

Question 6: What is an essential characteristic of resilience in project management?

Correct Answer: Recognizing and planning for the inevitable

Question 7: What should a project manager do if they are concerned about a project's timeline?

Correct Answer: Communicate your concern to the team and ask for more resources on the project

Question 8: What can a project manager do to mitigate potential delays in a project?

Correct Answer: Add task buffers

Question 9: What do project managers consider when identifying the critical path in a project?

Correct Answers: The tasks that can be performed in parallel, The path of work from the start to the end of the project

Question 10: Which of the following tools is commonly used for task management in projects?

Correct Answer: Trello